In the coming weeks, the final Tyra II pieces – two bridges and a flare – will be installed. PHOTO: Tyra II Process Module Sails Away from BatamĪfterward, they sailed one nautical mile to the final bare jacket while they raised the module by nine meters to then lower it onto the six legs.With two enormous crane hooks, the team picked up the process module from the heavy transport vessel GPO Emerald. Heerema said that the process required a lot of coordination, horsepower, and precision when the crew on Sleipnir had to install the enormous process module. Per Heerema, thanks to great weather conditions, the crane drivers got the green light to lift the module into its final position less than 24 hours after its arrival and four days ahead of schedule. The sea fastening helped to ensure a safe and stable journey from Indonesia.